		[Meeting of Directors held at Goodison Park
		15th February 1910]

Present		 D. Kirkwood Esq. Chair
		Messrs	Bainbridge
			Clayton
			Davies
			Kelly
			Wade
			Whitford
			Wilson

Investigation	Mr. Leitch the Architect was in attendance
of a/cs with	with plans, specifications &c.
Mr. Leitch	The Chairman, Dr. Whitford, having pointed
		out that the tenders given by Messrs Francis
		Morton & Co. & Bullen Bros. had been
		greatly exceeded & that the estimated
		cost of the work to be done by Mr. Leitch
		had also been considerably exceeded, the
		total excesses being roughly £6000. Mr. Leitch
		was asked what explanation he had to offer.
		The explanation offered by Mr. Leitch
		was as follows:-
 I	(A)	As to the Steelwork, the difference in the a/c
		of Mess. Fcs. Morton & Co. Ltd. amounting to a
		checked & reduced amount of £1600 is due
		in the first place to the extension of the
		front portion of the Directors Pavilion, increasing
		the accommodation of the upper deck for some
		600 persons and the lower deck for some
		1200 persons. This alteration in the plan was
		decided upon by the Directors, subsequently
		to Messrs Mortons tender having been accepted.