796EFC-1-1-29_0094a.tif
				     [REPORT OF GROUND COMMITTEE
				         1ST DECEMBER 1959]


			The Committee considered that a report should be made to the
		Board due to the very serious condition of the ground.

			After long consideration and observation the following conclusions
		were reached.

			The work performed on the ground in the close season was entirely
		successful as far as it went. The four inches of soil has been revitalised
		by cultivation and manuring, this being proved firstly by the excellent
		growth of grass, and secondly by the fact that when dug out the soil is
		saturated through, but the original trouble still remains, namely the panned
		2 or 3 inches above and below the heating wires.

			Up to the present time the top four inches have absorbed all the
		rain but the stage has now been reached when this top layer is saturated
		exactly like a sponge and is incapable of assimilating any more water. In
		this condition forking serves no useful purpose as the water simply backed
		up when the fork was withdrawn.

			It is obvious that only two methods can effect a cure (a) to
		remove the water by drying and then cover the bad sections to prevent the
		saturated state arising again (b) to get to the root of the trouble by
		providing adequate drainage.

			Regarding the first remedy, last week the old fashioned method of
		soaking up the water by blankets and wringing them out was tried. Whilst
		successful inasmuch as a great deal of water was removed from the pitch, and
		obviously any water taken away must improve the soil's powers of absorption,
		nevertheless the magnitude of the task by this method can only hope to touch
		the fringe of the trouble. Information is being sought as to other methods
		of drying.

			Regarding the covering of the worst parts of the ground, the question
		of suitable material is being gone into and prices obtained. The second
		method of adequate drainage has been fully investigated. Last week a trench
		was dug approximately 3 yds x 20" and 3 wires laid bare. It was found that
		after the top four inches which were soft and porous the 2 or 3 inches
		surrounding the wires, although slightly damp, were panned hard and was
		obviously allowing no water to pass. In addition the clinker was also panned.
		The clinker was thoroughly forked and loosened and the soil combined with some
		sand replaced.

			This was entirely successful as the portion treated was like a firm
		island in the middle of a quagmire.

			It was only possible to dig 2 more trenches but these were equally
		successful. Work on similar trenches is proceeding as far as possible but
		it is a slow job. Nevertheless every piece of ground treated in this way is
		an improvement and by staggering the trenches it is hoped that it will drain
		a certain amount of water from the surrounding land.

			The Committee consider that this is the only real solution to the
		problem and if further labour could be obtained the job could be accelerated.
		The only obstacle is the fact that workmen obtained from the Labour Exchange
		are usually unskilled and unless treated with care the wires might be damaged.

			The Committee are particularly anxious to avoid this but there is
		still the last resort of indiscriminate forking into the clinkers with the
		consequential damage to the wiring. The half of the ground nearest the
		Directors' Box, although soft, is in reasonable condition but it is considered
		due to the saturated condition of the other side water may be seeping through
		to the better side.