[SUB-COMMITTEE MEETING HELD AT GOODISON PARK
THURSDAY, 26TH APRIL 1956]
Present:- Mr. J. C. Sharp (Chair) and Messrs.
N. W. Coffey, T. C. Nuttall and C. E.
Balmforth, with the Secretary in
attendance.
THE FOLLOWING RECOMMENDATIONS WERE MADE
Flood- That the proposed Floodlighting Scheme, as planned,
lighting be proceeded with. The foundation work to be done
during the summer of 1956 and the erection of the
towers to be done during the summer of 1957, owing
to the delay in steel deliveries. The total cost
would be in the region of £38,000.
Ladies' That a Ladies' Room be provided over the office at
Room an approximate cost of £1,200.
Plumbing That a firm of insulating experts be asked to report
on the insulation of our water pipes and that the
Merseyside Plumbing Co. account of £543 for repairs
be passed for payment.
Visiting Dir- That these be re-positioned in five rows of six
ectors' Seats seats at the rear of the present position.
Trainers' Approval was given to the purchase of materials
Store Room amounting to approximately £40 for the provision
of a new store room for equipment and kit.
R. E. Searle
Harry Peers & Co. tender for steelwork reduced
by £650 for May 1957 delivery accepted. No
Steel to be acquired through Black Market, and
to be invoiced at Ruling price as and when
acquired. Agreed that we pay for the
foundation work when completed.