			[Meeting of Ground Sub-Committee
			held at Goodison Park, Saturday,
			28th July, 1934]

Present		Messrs W. C. Cuff, E. Green, & J. Sharp.

Laundry			It was agreed to accept Mr. C. R. Harris's
		estimate of £17.15.0, for the erection of a wooden
		casing to the Wash House; the work to be deferred
		for 2 or 3 weeks.

Police Accommodation	Decided to erect Four Concrete Boxes
		outside the playing pitch walls, for the use of the
		Police on match days, the work to be done by
		Messrs Tyson's Ltd.

Bullens Rd. &		It was also agreed to have a renewal
Gwladys St. Hoarding of this hoarding at the junction of Bullens Rd.
		Stand & Back Gwladys St.


					Confirmed as Correct.